To use the same acceptance procedure for the 3 use cases, a common commissioning procedure is defined to confirm the installations are ready for their evaluation.
The commissioning procedure considers the following aspects: the inspection of piping layout, the sensors and data acquisition operation, electric connection, hydraulic and thermal performance and the acceptance of Waste Heat Recovery System (WHRS) installation comparing design and real performance values.
Following the Scientific Coordinator’s suggestion the acceptance criteria will be defined by the technician, the RTD and the industrial partners, case by case, when the installation was ready for the commissioning.
The commissioning procedure is described in this document (D2.4) and it will be used in WP4 for the 3 use cases installations commissioning.